A lagrangian relaxation based forward-backward improvement heuristic for maximising the net present value of resource-constrained projects
- Publication Type:
- Conference Proceeding
- Citation:
- Lecture Notes in Computer Science (including subseries Lecture Notes in Artificial Intelligence and Lecture Notes in Bioinformatics), 2013, 7874 LNCS pp. 340 - 346
- Issue Date:
- 2013-12-01
Closed Access
Filename | Description | Size | |||
---|---|---|---|---|---|
2012007927OK.pdf | Published version | 234.79 kB |
Copyright Clearance Process
- Recently Added
- In Progress
- Closed Access
This item is closed access and not available.
In this paper we propose a forward-backward improvement heuristic for the variant of resource-constrained project scheduling problem aiming to maximise the net present value of a project. It relies on the Lagrangian relaxation method to generate an initial set of schedules which are then improved by the iterative forward/backward scheduling technique. It greatly improves the performance of the Lagrangian relaxation based heuristics in the literature and is a strong competitor to the best meta-heuristics. We also embed this heuristic into a state-of-the-art CP solver. Experimentation carried out on a comprehensive set of test data indicates we compare favorably with the state of the art. © Springer-Verlag 2013.